Chau Hiep Phat successfully completed the on-site AHU Replacement & Installation project for a prestigious 5-star hotel in District 1, Ho Chi Minh City in early February.
Our technical team implemented a distinctive approach to AHU transportation and installation, aimed at cost optimization and minimal hotel operational impact:
Instead of conventional transportation, wedismantled the AHUinto compact units (aluminum frame, coil, base, etc.) and manually transported them to each floors.
This method not only helps to overcome narrow passages such as stairwells and elevators, but also avoids dismantling the machine room door and surrounding walls.
Then, in the machine room, the entire AHU units were assembled by our team of skillful technicians, ensuring the system operates efficiently and stably.